Modification of hydraulic bolts for steam turbine couplings of Huaneng Qinbei Power Plant 5# and 6#1000MW units

Customer Name: Huaneng Qinbei Power Generation Co., Ltd.

Location: Wulongkou Town, Jiyuan City, Henan Province

Time: 2014.12.12/2015.04.16

Customer equipment: Harbin Auto 1000MW

Event: In 2014 and 2015, the steam turbine coupling hydraulic bolt modification project was carried out on the 5# and 6# units respectively. Our company was responsible for the boring of the inner hole of the coupling and the installation of the hydraulic bolt. The process was smooth, the delivery was timely, and the service was obtained. The owner’s approval.